Business Case
Assessment of industrial capacity and ensuring a smooth supplier ramp-up
For an aerospace client experiencing a sharp increase in production volume, SURFEO assessed the industrial capacity and supply chain of a strategic supplier and drew up a plan to ensure a smooth ramp-up.
Maintaining the ramp-up without compromising the supply chain
The historic ramp-up in civil aviation is primarily driven by the supply chain: by the end of March 2026, Airbus’s commercial aircraft order book stood at 9,037 aircraft, representing more than ten years of production at the targeted rate [1]. For the A320 family alone, the announced target is 70 to 75 aircraft per month by 2027 [2]. This trajectory places pressure on tier 1 and tier 2 suppliers, who must invest without any certainty regarding the stability of their workload [3].
A major player in the aerospace industry, facing a projected sharp rise in volumes, needed to ensure that a strategic supplier could actually cope with this increase. The challenge was to distinguish between installed capacity and capacity that could actually be utilised, and to identify capacity risks before they spread from one stage of the production line to the next.
SURFEO has been commissioned to carry out an industrial and supply chain assessment of this supplier, evaluate its capacity to support the ramp-up and develop a robust ramp-up plan.
From a capacity assessment to a security plan
SURFEO analysed the supplier’s entire industrial infrastructure, then modelled the workload and capacity in order to objectively assess the risks and draw up a ramp-up plan.
- 01
Diagnose
Workload/capacity balance, utilisation rate, availability of critical equipment, supply chain flows and performance.
- 02
Modelling
Workload/capacity by workshop and critical resource: demand, target output rates, cycle times, OEE, production schedules.
- 03
Identify
Bottlenecks, risks of capacity saturation, dependence on suppliers and discrepancies between installed and available capacity.
- 04
Secure
Scaling-up plan: capacity, resources, investment, procurement and performance indicators.
Production rates in the aerospace sector are being held back by the production line’s capacity
- A320 family (late 2027)75 units per month
- A220 (2028)13 units per month
- A350 (2028)12 units per month
Airbus, Q1 2026 results, April 2026 [2]
- Airbus’s order book stood at a record 9,037 aircraft at the end of March 2026, representing more than ten years of production at the targeted rate [1].
- The A320 family is set to reach a production rate of 70 to 75 aircraft per month by 2027, compared with the initial target of 75 set for 2026 [2].
- The constraint is no longer commercial but industrial: bottlenecks and critical suppliers under pressure are dictating the production rate [3].
A targeted and secure ramp-up plan
A fact-based view
Objective mapping of capacity risks and discrepancies between installed and deployable capacity.
Identified bottlenecks
Bottlenecks, capacity constraints and supplier dependencies identified through modelling.
Security Plan
Capacity optimisation, investment, procurement and strategic stockholding.
Controlled ramp-up
A robust ramp-up plan, supported by performance indicators.
- Air Journal [1] Airbus: 114 aircraft delivered, 398 net orders and an order book of 9,037 aircraft as at 31 March 2026, April 2026. https://www.air-journal.fr/2026-04-29-airbus-114-avions-livres-398-commandes-nettes-et-un-carnet-de-9-037-appareils-au-31-mars-2026-5274843.html
- Air Journal [2] Airbus ramp-up: A320 family to 70–75 aircraft per month by 2027, A220 and A350 by 2028, April 2026. https://www.air-journal.fr/2026-04-29-airbus-114-avions-livres-398-commandes-nettes-et-un-carnet-de-9-037-appareils-au-31-mars-2026-5274843.html
- Industry Magazine [3] Aerospace: the 2026 ramp-up under logistical strain, 2026. https://industrie-magazine.fr/aeronautique-la-montee-en-cadence-2026-sous-tension-logistique/