
Business Case
Planning and ensuring the safety of a complex energy infrastructure project
For a major player in the energy sector, SURFEO structured, consolidated and managed the master schedule for a complex infrastructure project in order to ensure the reliability of milestones, interfaces and management decisions.
Improving the reliability of the schedule for an energy infrastructure project
Growing demand for electricity and the expansion of energy systems are increasing the need for reliable infrastructure. In 2024, global investment in the energy transition reached a new record of USD 2,400 billion, of which approximately USD 807 billion was allocated to renewable energy alone, with 96 per cent of this directed towards the electricity sector [1]. This trend is leading to a proliferation of major projects, the management of which has become more complex, time-consuming and contentious: timelines are lengthening, costs are rising, and the failure to anticipate difficulties in implementation and coordination between stakeholders is rarely brought under control [2].
For a major player in the energy sector, coordination between engineering, procurement, construction, commissioning and management required a shared planning framework capable of consolidating progress and anticipating the impact on key dates.
SURFEO provided support for planning and project control, from the structuring of the WBS through to the analysis of the critical path and the implementation of performance indicators.
From the master schedule to critical path management
SURFEO worked in coordination with the engineering, procurement, construction, commissioning and project management teams to establish a reliable, shared planning framework.
- 01
Organise
Definition of the WBS, activities, milestones and interfaces between work packages.
- 02
Plan
Drawing up and updating the master schedule and lot-by-lot schedules.
- 03
Analyse
Incorporation of progress, critical path, margins, dependencies and constraints.
- 04
To drive
Project Controls KPIs, dashboards, progress charts and scenarios.
Managing deadlines: a recurring weakness in major projects
- Budget overrun45%
- Missed deadline7%
- Delivery value deducted56%
Sectoral study covering more than 5,400 projects, published in 2025 [3]
- Investment in the energy transition reached a record high of US$2,400 billion in 2024, of which US$807 billion was spent on renewables [1].
- Large-scale projects exceed their budget by an average of 45 per cent and their deadline by 7 per cent, whilst the value delivered is 56 per cent lower than forecast [3].
- A failure to anticipate difficulties in implementation and in coordinating the various stakeholders is one of the main causes of the project going off course [2].
More reliable planning management and sound decision-making
Shared repository
Consolidated master schedule, shared across all work packages and interfaces.
Anticipated risks
Deviations, dependencies and variances are monitored to anticipate their impact on milestones.
Informed decisions
KPIs, dashboards and scenario analyses to support management.
Improved reliability of control systems
Comprehensive project management, with a focus on the critical path.
- IRENA [1] Global investment in renewable energy reaches US$807 billion in 2024, November 2025. https://www.irena.org/News/pressreleases/2025/Nov/Global-Renewable-Energy-Investment-Hit-USD-807-Billion-in-2024-FR
- Office of the High Commissioner for Strategy and Planning [2] Major infrastructure projects: prioritising, simplifying, succeeding, January 2026. https://www.strategie-plan.gouv.fr/publications/grands-projets-dinfrastructures-prioriser-simplifier-reussir
- Sector study (trade press) [3] Study of over 5,400 projects: average budget overrun of 45 per cent and average delay of 7 per cent; a 56 per cent lower figure, projected for 2025. https://perfsystemique.fr/pourquoi-les-projets-ralentissent-execution/

